The job at a glance

Scope, location and what was specified.

Location
Truxton AvenueWestchester, Los Angeles 90045
Roof area
22 squaresRoughly 2,200 square feet
Scope
Full re-roofNew solid sheathing throughout
Permit
Pulled and closedLADBS #25016-90000-19120
LADBS express permit inspection record for a roof replacement in Westchester, Los Angeles

What the permit specified

  • Class A or B roof covering weighing under 6 pounds per square foot, installed over new solid sheathing.
  • Cool Roof compliance. Because the replacement covered more than 50% of the roof area, a CRRC-certified Cool Roof product was required under Title 24.
  • Express Permit, no plan check. Filed and issued the same day, 14 June 2025.
  • Two inspections passed. OK to Cover signed 18 June 2025, project final signed off later the same month.
  • Photographed daily from the air. The drone footage above runs in job order, from tear-off on the morning of 16 June to the finished roof on 23 June.

The permit record for this job, shown as issued. The owner name and street number are redacted. Click to open it full size.

New solid sheathing being laid on a Westchester roof replacement in Los Angeles

The deck came off too, not just the covering

The permit called for new solid sheathing across all 22 squares, which is what separates a re-roof from a resurface.

Plenty of re-roofs stop at the covering: strip the old material, lay new underlayment on whatever deck is already there, finish. That works when the sheathing is sound. It does not when the deck itself has taken years of moisture.

This job was permitted for new solid sheathing throughout, so the structure under the roof was replaced rather than reused. It costs more up front and it is the difference between a roof that lasts its rated life and one that fails early from underneath.

Westchester sits close enough to the coast for salt air and marine layer, and far enough inland to take the full run of summer UV. Roofs here age from both directions at once.

How we decide repair vs. replacement →

Seven days apart

The same roof from the air, mid-rebuild and finished.

Westchester roof mid-replacement with new sheathing down, Los Angeles
17 JuneDeck stripped and new sheathing laid
Completed roof replacement on a Westchester home in Los Angeles
23 JuneFinished roof, seven days later

How the job ran

Four stages, same sequence as every replacement we take on.

  1. Assessment

    We walked the roof, photographed the condition and checked the underlayment where we could reach it, then put the findings in writing before quoting anything.

  2. Permit

    Truxton Avenue sits inside City of Los Angeles limits, so this was filed with LADBS as an Express Permit, issued 14 June 2025 with no plan check required.

  3. Tear-off and new sheathing

    Existing roof stripped, new solid sheathing laid across all 22 squares, then the Class A rated covering installed and every penetration reflashed. Inspector signed OK to Cover on 18 June 2025.

  4. Final inspection

    Drainage checked, debris and fasteners cleared from the property, project final signed off by LADBS and the closed permit handed to the owner.

Day by day from the air

Six frames from the drone record, in the order the job ran.

Start of tear-off on a Westchester roof replacement in Los Angeles
Mon 16 June, 9:00am Tear-off begins on the original covering.
Westchester roof stripped to the deck at the end of day one
Mon 16 June, 3:40pm End of day one, roof stripped back.
New solid sheathing being installed on a Los Angeles roof
Tue 17 June, 2:04pm New solid sheathing going down across all 22 squares.
Roof covering installed on a Westchester home in Los Angeles
Thu 19 June, 1:53pm Covering installed, day after the OK to Cover inspection.
Completed edge and ridge detail on a Westchester roof
Mon 23 June, 1:49pm Detail and edge work complete.
Finished roof replacement in Westchester, Los Angeles
Mon 23 June, 1:47pm Finished roof, permit closed.